Civic Mobility Program

The 2 km Loop & Bottleneck Solutions

A phased, citizen-led effort by Nallurahalli residents and Whitefield Rising to eliminate traffic choke points, underground cables, and establish a permanent one-way circulation loop around Nallurhalli Metro.

Choke Point 1: 40m Bottleneck (Completed & Curing)
Choke Point 2: Shiva Temple (Active ₹17L Campaign)
40m Point 1: Paved & Widened
7 Poles Point 2: In Carriageway to Remove
₹17 L Active Fund Target (80G)
2.2 km One-Way Loop Length
Current Active Priority

Choke Point #2: Shiva Temple Junction — Underground Cables & Remove 7 Poles

Seven high-tension and distribution electrical poles stand directly in the roadway at the Shiva Temple / Bro Chemist junction, choking traffic into a dangerous single file. Here is our plan to remove them.

Interactive View: Shiva Temple Junction (With Poles vs. Cleared Roadway)

Drag the slider to see how moving cables underground will reclaim the full width of the carriageway.

Proposed after: Shiva Temple junction with poles removed and carriageway clear Proposed: Cables Underground & Poles Cleared
Current before: Shiva Temple junction with electric poles in the carriageway Current: 7 Poles in Carriageway

Interactive View: Commercial Stretch (Bro Chemist Corner)

Drag the slider to see the reclaimed lane on the connecting commercial corridor.

Proposed after: Bro Chemist road with poles removed Proposed: Unblocked Lane
Current before: Bro Chemist road with pole obstruction Current: Obstruction in Road
Community Campaign
Target Budget: ₹17 Lakhs
Timeline once funded: ~2 Months
Campaign initiated across 15+ apartment communities Goal: ₹17,00,000
Beneficiary Account Whitefield Rising Trust
Tax Benefit 80G Tax Exemption Eligible
Scope of Work Underground cabling & 7 pole removals
Approval Status BESCOM Joint Inspection Passed (Oct 2026)
Note on funding: BESCOM has approved technical supervision for self-execution, but requires the capital cost to be funded by the community. Join our WhatsApp group to get direct bank/UPI transfer details and tax receipts.
Completed Choke Point

Choke Point #1: 40m Bottleneck at 15 New Temple Road

For years, this 40-metre stretch narrowed to a single lane between stone compound walls. Opposing cars could not pass, trapping traffic for kilometres. Through constructive civic dialogue with the local landholders, permission was given to pave and open the full road width.

Interactive View: 15 New Temple Road Before & After

After: Widened roadbed with steel rebar laid for concreting Now: Widened & Paved
Before: Narrow choke point with stone wall and blue sheet barricade Before: 40m Bottleneck

Sunday Concreting: Community at Work

Watch residents, volunteers, and engineering teams pour and finish the 40-metre stretch on October 4, 2026.

Ground footage: Concreting the bottleneck at 15 New Temple Road.

Residents lining up to pass concrete buckets Community Bucket Line
Spreading and leveling concrete Leveling & Finishing
Deccan Herald Newspaper coverage Deccan Herald Coverage
Traffic Masterplan

The 2.2 km Circulation Loop

Connecting Varthur Road, New Temple Road, 2nd Main, and Nallurahalli Main Road in a continuous clockwise flow to eliminate bi-directional gridlock.

Aerial Satellite Map of the 2.2 km Nallurahalli Loop Route

Key Loop Milestones & Waypoints

1

Head Start Montessori

Entry junction connecting Varthur Main Road to the interior loop.

2

15 New Temple Road

Choke Point #1: 40m bottleneck successfully concreted on Oct 4.

3

Shiva Temple Junction

Choke Point #2: 7 electric poles in roadway undergoing ₹17L cabling drive.

4

S R Photo Studio & 2nd Main

Turn toward Nallurahalli Main Road with planned pedestrian sidewalk.

5

Dhaba Square / Borewell Jn

Northeast corridor connecting toward Whitefield Post Office / ECC Rd.

6

Siddapura Main Road

Southward return corridor passing Truffles & Shell / HP fuel outlets.

Milestones

The Journey to a Functional Loop

From neighbourhood protests to collaborative engineering with civic bodies.

MID OCT 2026 CURRENT

BESCOM Joint Inspection & ₹17L Drive Launched

Joint site inspection conducted with BESCOM engineers for Shiva Temple junction. Technical clearance confirmed for undergrounding cables and removing 7 road poles. ₹17 Lakh fundraising launched via Whitefield Rising Trust.

SUN 4 OCT 2026 COMPLETED

40m Bottleneck Paved with Concrete

Community volunteers and engineering workers poured reinforced concrete over the 40-metre stretch on New Temple Road, funded by ₹4 Lakhs of resident contributions.

Read Times of India report ↗
SEP 2026 CONSENSUS

Landowner Agreement & Crowdfunding

Landowners generously agreed to grant public right-of-way while retaining property title, breaking a multi-year deadlock without costly litigation.

MAR 2023 TRANSIT BOOM

Nallurhalli Metro Station Opens

Namma Metro Purple Line brings thousands of daily commuters to Nallurhalli, making the 2 km loop critical for last-mile connectivity.

Agency Roadmap & Shared Responsibility

Achieving a permanent solution requires coordination between civic agencies and citizen initiatives:

Task / Milestone Responsible Stakeholder Status
40m Curing & Barricades Nallurahalli Residents Curing Complete (~Oct 18)
Shiva Temple 7-Pole Cable Undergrounding Whitefield Rising + BESCOM Fundraising (₹17L Target)
One-Way Signage & Police Deployment Whitefield Traffic Police Formal Order in Progress
Stormwater Drain (SWD) Slabs & Sidewalks BBMP / GBA East Representation Submitted

Be Part of the 2 km Solution

Whether by contributing to the Shiva Temple ₹17L cable undergrounding drive, sharing the campaign video, or volunteering on-ground — your participation counts.

Join the WhatsApp Community